Project critical path

Plan a project from its tasks: find the critical path, spare time for every task, a Gantt chart, real dates and the chance of finishing on time.

Tasks (use the codes in “Waits for”, separated by commas)
CodeTaskDaysWaits forRemove

critical task   other task   spare time

How to use

  1. List the tasks with how many days each takes. In Waits for, type the codes of the tasks that must finish first, such as A, C.
  2. The planner works out the shortest possible length of the project and the critical path: the tasks that cannot slip without delaying the end.
  3. The Gantt chart shows when each task can start; the thin bar after a task is its spare time (float).
  4. Not sure how long tasks take? Tick Uncertain times and give a best, likely and worst case to see the chance of finishing by a deadline.
  5. Add a start date to see real dates. Your plan is kept in this browser; save a CSV to keep or share it.

Keyboard and touch

TabMove across the task table, box by box
EnterAccept a value and update the plan
↑ ↓Change a number of days

Tips

  • To finish sooner, shorten a task on the critical path. Shortening any other task changes nothing until it becomes critical.
  • Total spare time (total float) is how long a task can slip without delaying the project; free float is how long it can slip without delaying the next task.
  • A task with 0 days is a milestone, such as “approval received”.
  • The PERT estimate (best + 4 × likely + worst) ÷ 6 is a little longer than “likely” when things tend to go wrong.
  • If the planner reports a loop, two tasks are each waiting for the other. Remove one of the links.

About this planner

It uses the critical path method (CPM, 1950s): a forward pass gives each task’s earliest start and finish, a backward pass from the end gives the latest, and tasks whose earliest and latest starts are equal are critical. Finish-to-start links are used, the most common kind.

PERT (Program Evaluation and Review Technique) uses each task’s expected time (o + 4m + p) ÷ 6 and variance ((p − o) ÷ 6)². The chance of finishing on time uses the critical path with the largest variance and a normal distribution, which is an approximation. The tests compare results with an independent calculation in Python on random projects.

Your plan stays in your browser. Nothing is uploaded.